Uncategorized

May 9 update

18 rock wall is starting to pick up steam as the bottom course is now almost complete.

I would anticipate the rock wall to be finished by next Wednesday and soil and grading finish in another week.

The staff finished 2 fairway bunker and has started on 4 Fwy bunker as of today. Sod is expected this Tuesday.

Monday was our first closing and we solid tined aerify the greens followed by 2 vertical mowings and topdressing. Greens are putting in the slow side because of these practices and will improve as the week progresses.

4 Fwy bunker nose removal Vertical mowing “verticutting”Verticutting lines2 Fwy bunker awaiting Sod 2 Fwy drainage